| Risk Matrix: |
| 1. No one risk matrix is correct for every project, however some degree of consistancy is recommended for any one project. |
| 2. Risk is a number that is the severity number times the likelyhood number. Where severity and likelyhood are numbers 1 to 3, then risk is numbers 1 to 9. Where severity and likelyhood are numbers 1 to 5, then risk is numbers 1 to 25. |
| SIMPLE: (Red-Amber-Green) |
| 3. A simple risk matrix may involve Level of Harm or severity as: |
| (1) Low severity as slight injury as scratch or cut. |
| (2) Medium severity as a serious injury with up to 3 days off work. |
| (3) High severity as a major injury including incapacity or death. |
| 4. A simple risk matrix may involve a possibility of likelyhood as: |
| (1) Low possibility as very unlikely or unlikely or not forseeable. |
| (2) Medium possibility as possible and will happen occationally. |
| (3) High possibility as certain to happen. |
| 5. A simple risk priority is severity times likelyhood as: |
| (1-3) Low priority. |
| (4-6) Medium priority. |
| (7-9) High priority. |
| COMPLEX: |
| 6. A complex risk matrix may involve Level of Harm or severity as: |
| (1) Trivial severity as slight injury such as a scratch. |
| (2) Minor severity as a minor injury such as a cut. |
| (3) Off Work severity as a serious injury with 1 to 3 days off work. |
| (4) Major severity as a serious injury with more than 3 days off work. |
| (5) Incapacity severity as incapacity or death. |
| 7. A complex risk matrix may involve a possibility of likelyhood as: |
| (1) Very Unlikely and not forseeable. |
| (2) Unlikely possibility. |
| (3) Possible possibility and will happen occationally. |
| (4) Probable possibility and will happen. |
| (5) Certain possibility. |
| 8. A complex risk priority is severity times likelyhood as: |
| (1) Very low priority. |
| (2-4) Low priority. |
| (5-9) Medium priority. |
| (10-12) High priority. |
(13-25) Urgent action needed.| Form: | | 1a. Project Name (Project) | | 1b. Project No (Project) | | 1c. Name of Client (Project) | | 1d. Work Location (Project) | | 2. Date of Risk Assessment | | 3. Hazard | | 4. Persons at risk | | 5. Consequence | | 6. Assessment Level of Harm (low, medium high) | | 7. Assessment Likelihood (low, medium high) | | 8. Assessment Risk Rating (6*7) | | 9. Control Measure List (10 * 128) | | 10. Residual Level of Harm (low, medium high) | | 11. Residual Likelihood (low, medium high) | 12. Residual Risk Rating (10*11)| Hazard Pages: | | 4410. Hazard Guide (this page) | | 4414. Hazard Form (readonly) | | 4415. Hazard Sheet | | 4416. Hazard Form (new and change) | | 4417. Hazard Archive | 4418. Hazard History| Data: | | B41.01.08.INT. Primary Key | | B41.03.08.INT. Project Key | | B41.04.08.INT. HRA Key | | B41.20.08.INT. Who Created ID | | B41.21.08.INT. Date Created | | B41.22.08.INT. Time Created | | B41.23.08.INT. Assessment Level Of Harm | | B41.24.08.INT. Assessment Likelihood | | B41.25.08.INT. Assessment Risk Rating | | B41.26.08.INT. Residual Level Of Harm | | B41.27.08.INT. Residual Likelihood | | B41.28.08.INT. Residual Risk Rating | | B41.29.32.TXT. activity name | | B41.30.64.TXT. Hazard name | | B41.31.32.TXT. People | | B41.32.64.TXT. Consequence | | B41.40.08.INT. Control Measure 0 | | B41.41.08.INT. Control Measure 1 | | B41.42.08.INT. Control Measure 2 | | B41.43.08.INT. Control Measure 3 | | B41.44.08.INT. Control Measure 4 | | B41.45.08.INT. Control Measure 5 | | B41.46.08.INT. Control Measure 6 | | B41.47.08.INT. Control Measure 7 | B41.48.08.INT. Control Measure 8| Control Measure: | | ZB41.01.08.INT. Primary Key | | ZB41.02.08.INT. Language ID | | ZB41.03.32.TXT. Subject (noun verb) | ZB41.04.128.TXT. Control Measure (what to do)| Document Control: | | 1. Document Title: Risk Assessment Statement. | | 2. Description: Risk Assessment Statement. | | 3. Keywords: ITIL OHS, HSE, Risk Assessment Statement. | | 4. Reference: 161535. | | 5. Privacy: Public education service as a benefit to humanity. | | 6. Issued: 13 Feb 2017. | | 7. Edition: 2.2. |
|
|
|
|
|